Application for permission to bring judicial review
[2025]JCA005
Court of Appeal
6 January 2025
Before :
|
Sir William Bailhache, President;
Helen Mountfield KC JA, and;
The Rt Hon James Wolffe KC JA.
|
Between
|
Bretagne, Angleterre, Irlande SA
|
Appellant/Respondent (to Judicial
Review and to the cross-appeal and to application to set aside)
|
And
|
Minister for Sustainable Economic
Development
|
Respondent to Appeal and
Cross-Appellant / Respondent (to judicial review)
|
And
|
DFDS / AS
|
Interested Party
|
Advocate R. J. McNulty for the
Appellant/Respondent.
Advocate M. St J. O’Connell for the Respondent
to Appeal and Cross-Appellant.
Advocate S. Williams for the Interested Party.
DECISION AND SUMMARY OF REASONS
mountfield ja:
Introduction
1.
This
hearing is to hand down our decision in relation to the applications for leave
to appeal the decisions of the Royal Court (Commissioner Thompson) on 20 and 31
December 2024. There were three
applications for leave, which all arose from an application to bring
proceedings for judicial review in relation to the Minister’s decision to
grant DFDS preferred status as the successful bidder in the contract for the
provision of ferry services to the Island of Jersey for a minimum period of 15
years with effect from 25 March 2025, when the current contract which is held
by Condor Ferries Limited (“Condor”) expires. The ferry services which form the
subject matter of these proceedings are lifeline services for the Island of
Jersey, being the means by which essential supplies are brought to the island.
2.
In the
latter stages of the procurement process, there were two bidders for this
contract: Bretagne Angleterre Irlande SA (“Brittany Ferries” ) is
the 51% shareholder of Condor Ferries (the proposed operator), and another
ferry service provider called DFDS/AS (“DFDS”). As unsuccessful bidder, Brittany
Ferries, sought to challenge two decisions by way of judicial review. The first was the Minister’s
decision of 7 November 2024 to terminate an earlier procurement exercise. The second challenge was to the decision
of 3 December 2024 to award the franchise from March 2025 to DFDS, the
successful bidder.
3.
The
proceedings were lodged on 18 December 2024, but necessarily the courts moved
quickly, because of the extreme importance of matters proceeding swiftly to
ensure that these services continue to be in place from the end of the existing
contracted provision and the start of the new contract. We will set out a little more detail
about the background to the appeals before us in a moment.
4.
In
summary, we heard three appeals on 3 January 2025, against the
Commissioner’s decisions of 20 and 31 December 2024. (We gave notice to the parties prior to
the appeal that given the urgency in dealing with the matters raised, we would
hear the applications for leave and the substantive appeals together).
This is our decision in relation to those
applications.
Our decision on the appeals
Our decisions are:
(i)
We allow
the application by the Interested Party, DFDS, to appeal against the refusal to
set aside the leave given to Brittany Ferries to challenge the decision of 3
December 2024 by way of judicial review and allow the appeal.
(ii) We refuse the application by Brittany Ferries
for leave to appeal against the Commissioner’s decision to refuse
permission to challenge the decision of 7 November 2024 to terminate an earlier
procurement process which had been commenced by the States of Guernsey and the
Government of Jersey jointly, to commission ferry services to the islands of
Jersey and Guernsey. We also refuse
Brittany Ferries’ application for leave to appeal against the
Commissioner’s decision to refuse them permission to challenge the decision
of 3 December 2024 on the basis of an alleged failure to give adequate reasons
for the decision.
(iii) It follows that the judicial review proceedings
are at an end, and we set aside the grant of permission and vacate the hearing
listed for 13 and 14 January 2025.
(iv) It also follows that we also grant the Minister
leave to appeal against the
Commissioner’s decision to grant permission to challenge his decision by
way of judicial review and allow the appeal.
(v) We are presently minded to award the costs of
and occasioned by this appeal to the Minister and to DFDS as the successful
appellants. However, this is
subject to any submissions which the parties may wish to make on this, and we
will set out a timetable acceptable to the parties for the making and consideration
of such submissions.
5.
A fully
reasoned judgment will be handed down at a later date. We give brief reasons for our decisions
now – which will be expanded upon in the judgment to come. The written reasons which will follow in
due course will be the authoritative judgment.
A short summary of the factual background
6.
A summary,
which he recognised would necessarily be partial and incomplete, of the general
factual background to this challenge was set out in the Commissioner’s
judgment of 24 December 2024 at paragraphs 3-65 (Bretagne Angleterre Irlande
SA v Minister for Sustainable Economic Development [2024] JRC 292). It is unnecessary to repeat it here.
7.
In short,
the current procurement process arose after the termination of an earlier
procurement process, referred to by the Commissioner as the Channel Island
Procurement Process which ran between May and October 2024, and intended to be
held jointly with the States of Guernsey. The Channel Island Procurement Process
had resulted in two bidders submitting tenders and invitations to negotiate:
Brittany Ferries and DFDS.
8.
At the end
of that process, the States of Guernsey considered that Brittany Ferries had
the stronger bid. The Government of
Jersey had further questions which it considered should be addressed before a
decision was reached. However, on
30 October 2024, the States of Guernsey reached a unilateral decision to
procure services from March 2025 from Brittany Ferries, without awaiting the
result of enquiries which the States of Jersey considered necessary to reach a
proper decision. On the same date,
the Chief Minister and the Minister requested Brittany Ferries attend a meeting
to answer some questions they had in relation to the bid. A further question about which party
– Brittany Ferries or Condor – would be the counter-party, was put
in writing on 1 November 2024, and Brittany Ferries responded.
9.
On 6
November 2024, Mr Andrew Scate, Senior Responsible Officer for the procurement
process informed Brittany Ferries orally (and confirmed in writing on 7
November 2024) that the joint
Channel Island Procurement process was terminated (as paragraphs 3.2 and 105 of
the Invitation to Tender permitted).
10. Mr Scate informed Brittany Ferries that the
Government of Jersey would start a fresh procurement process for a
‘Jersey-only’ Ferry Services Operator. He said that it would not be appropriate
to compromise or contaminate this new process (i.e. act unfairly to other
prospective bidders) by entering discussions about the terminated process ahead
of the launch of the new one.
Condor was invited to extend the existing contract by seven months so as
to allow the new procurement process to be conducted.
11. On
11 November 2024, Mr Mathieu of Brittany Ferries raised concerns about what he
said were lack of openness and transparency about the reasons for
termination. He also raised
concerns about potential bias, arising from two matters. The first was the previous involvement
of a Senior Responsible Officer, Mr Corrigan, who had expressed views on the
best bidder in the previous process in the course of a public consultation on
the matter. (That SRO had since
recused himself and taken no further part in the process: he was not a decision
maker). The second of public
observations of Deputy Kirsten Morel, which he said indicated bias against
Brittany Ferries.
12. Critically to this appeal, he said that he
“explained that Condor would not be able to accept the proposed 7 month
contract extension”. He also
explained that BAI/Condor did not intend to participate in the process
described for a Jersey-only solution given what he said was a “lack of
confidence in the integrity and impartiality of Deputy Morel”.
13. On 13 November 2024, the Minister made a public
statement in the States of Jersey which was subsequently relied upon, together
with the involvement of Mr Corrigan in the Channel Island Process, as
indicating apparent bias in favour of DFDS.
14. However, following further correspondence
(which included an explanation by the Chief Minister to Mr Mathieu that
‘we remain in a process with DFDS and we must be fair and equitable to
all parties’ and specific encouragement to Brittany Ferries to
participate in the Jersey-only process, they decided on 18 November 2024 to set
aside their decision not to participate, and indicated that they would
participate in the new tender process, albeit ‘reserving all
rights’ in relation to a prospective challenge to the impartiality of the
Minister. Brittany Ferries did
indeed lodge a tender on 27 November 2024.
In this tender, it was the bidder and operator, with Condor Ferries
discharging the obligations of operator by way of subcontract.
15. Pausing there, we see it as a significant part
of the factual background in this case that the Minister invited Condor to
extend the existing contract by seven months to allow a fresh procurement
exercise to be considered and undertaken, but Brittany Ferries as
Condor’s parent company refused that request. This is essential background. It meant that the second procurement
process had to be undertaken with great haste. Affidavit evidence put in on the eve of
the 18 December hearing on behalf of the Minister explained the way the
Minister went about this process, which involved:
(i)
Taking
active steps to encourage both previous bidders to bid in the second process;
(ii) Publishing new (slightly adjusted) criteria -
using essentially similar criteria to the previous procurement process but,
among other changes, amending the terms of the legal criterion which had
resulted in a ‘technical fail’ for DFDS in the Channel Island
Process;
(iii) More extensive involvement than in the first
process of external consultants, KPMG, to assist with the assessment and
scoring of the two bids;
(iv) Independent separate assessments of the bids by
civil servants, who put in affidavit evidence (to us – not available at
the time of the expedited leave hearing before the Commissioner) as to the
process they undertook and their reasoning.
16. On
3rd December 2024 Mr Scate telephoned Brittany Ferries to inform
them of the Minister’s decision that following the expedited second
process, the contract for Ferry
Services from 25 March 2025 would be awarded to DFDS. This decision was communicated in
writing on 4 December 2024.
17. Mr Mathieu says that he complained that no
reasons were given for the decision in the telephone conversation on 3rd
December 2024, but external legal advisors retained by Brittany Ferries first
wrote to seek reasons both for the decision to award the contract to DFDS and
the earlier decision of 7 November 2024 to terminate the Channel Island
Procurement Process more than a week later, on 11 December 2024. Mr Scate responded setting out scores
and reasons in an Excel spreadsheet which had been used to ‘objectively
assess and give value to the key criteria across each of the bids’ as evaluated
and overseen by KPMG along with GoJ Technical advisors”. On the basis of those scores, DFDS
scored 74% and BAI scored 55%. Mr
Scate also gave a brief narrative synopsis of the differences between the bids,
quoted in paragraphs 38 and 41 of the Commissioner’s decision.
18. Mr Scate’s evidence on behalf of the
Minister summarised concerns about the Brittany Ferries bid and stated (at
paragraph 9.9):
“I wouldn’t say we
were biased. I certainly think we
were looking for a company that does not have clear and present financial
issues, which would mean that these services cease operating which would put
Lifeline Services at risk. We
don’t want that. We want a
service that just operates properly and that we don’t have to worry
about. And that, fundamentally, is
what we have been trying to achieve”.
19. The contract for provision of Ferry Services
with DFDS was indeed entered into on 31 December 2024 (when a stay agreed by
the Minister came to an end), and DFDS has lodged evidence explaining the
extensive logistical steps it has taken including tens of millions of euros of
expenditure, to ensure that it is in a position to commission these services by
March 2025.
The Proceedings giving rise to these appeals
20. The application by Brittany Ferries for leave
to bring proceedings for judicial review was lodged on 18 December 2024, and
heard on 20 December 2024. The
parties were agreed as to the test for leave, which is that set out in the
decision of the Privy Council in Sharma v Browne-Antoine [2006] 1 WLR
780 at para 14.4
“The ordinary rule now is
that the court will refuse leave to claim judicial review unless satisfied that
there is an arguable ground for judicial review having a realistic prospect of
success and not subject to a discretionary bar such as delay or an alternative
remedy …. But arguability cannot be judged without reference to the
nature and gravity of the issue to be argued. It is a test which is flexible in its
application”.
21. On 20 December 2024, the Commissioner granted
leave to apply for judicial review of the decision reached on 3 December 2024
by the Minister for Sustainable Economic Development (“the
Minister”) not to award a long-term ferry contract to Brittany Ferries
and instead to award it the Interested Party, DFDS. He granted that leave on limited
grounds: allegations of a breach of the duty of procedural fairness and
apparent bias. He refused
permission on the basis of an allegation of failure to provide reasons.
22. First, he granted leave only in respect of the
3 December 2024 decision to award the contract to DFDS. He refused to grant leave to challenge
the earlier decision of the Minister, notified to Brittany Ferries on 6
November 2024, in relation to the earlier joint procurement exercise with the
States of Guernsey.
23. Secondly, he granted leave only on the grounds
of alleged procedural fairness and apparent bias. He restricted his decision on
arguability on grounds of apparent bias to the statement of the Minister on 13
November to the States and whether there was evidence of predisposition towards
DFDS on that basis, and on the basis of the alteration of the criterion on the
basis of which DFDS had scored a mandatory fail in the Channel Islands
Process. He refused to consider the
prior involvement of Mr Corrigan in the first process, who was by then out of
the picture, and observed that “Brittany Ferries only just got over the
threshold for giving leave on this ground”. He refused leave in relation to a third
intended ground of challenge, namely a failure to give adequate reasons for the
decision of 3 December 2024.
24. He also observed (para 133) that the decision
on leave may have significant ramifications for the Government of Jersey and
its desire to enter into a contract with DFDS, but held that ‘that is not
a relevant consideration in relation to whether or not to grant leave if the
relevant test is met and a trial is required…’.
25. DFDS subsequently brought an application under
Royal Court Rule 16/6 to set aside the decision to grant leave on the basis of
delay and its consequences in relation to detriment to good public
administration and third party interests.
It submitted that this was an argument in relation to which it contended
Brittany Ferries had not been entirely frank (as to the date of its state of
knowledge about the remedies open to it), and which the Commissioner had not
addressed in his 20 December decision or 24 December judgment. DFDS submitted that it suffered serious
prejudice as a result of this delay – a submission supported by evidence
lodged by DFDS and summarised in its skeleton argument. It averred that the Commissioner had
erred in failing to address these matters, which were not properly put before
the Court. These submissions were
supported by the Minister.
26. In view of the urgency of the matter, and the importance
of the decision to award a new ferry contract for Jersey, the learned
Commissioner considered this application on the papers only. On 31 December, he handed down written
reasons for refusing it (Bretagne Angleterre Irlande SA v Minister for Sustainable
Economic Development [2024] JRC 297).
Short Summary of our reasons
27. We have convened the Court today to give our
decision on the applications before us.
We are providing a short summary of our reasons for the decisions now,
to assist with public understanding of them. However, the authoritative written
reasons for the decisions will follow in due course.
28. In short, we consider the Commissioner was
mistaken in the approach which he took to determining the set aside
application. In our view, the application
for leave was insufficiently prompt, and the grant of relief would cause
substantial prejudice to the rights of DFDS and – more importantly
– detriment to good public administration and the safety of the Island.
29. Rule 16/3 of the Royal Court Rules provides, in
rule 16/3 (1) and (2) that leave to apply for judicial review must be brought
“promptly, and in any event not later than 3 months from the date when
grounds for the application first arose” and that “the
Bailiff may refuse an application made within the period of 3 months if
satisfied that the application is not sufficiently prompt AND that if the
relief sought were granted, on an application made at this stage, it would be
likely to cause substantial hardship to, or substantial prejudice to, the
rights of any person or be detrimental to good administration”.
30. There is accordingly a duty on an applicant for
judicial review to bring the application promptly. The question of whether an application
has been brought sufficiently promptly will depend on the circumstances. In particular, the impact of the passage
of time on third parties and on good administration is a material consideration
in determining whether or not an application has been brought sufficiently
promptly.
31. There is extensive authority –
which we will set out in our full judgment in due course – that in a case
where delay may cause serious detriment to the public interest in terms of good
public administration, and/or commercial interests, then an application may
require to be brought within days not weeks or months. Moreover, what amounts to a
‘prompt’ application depends in part on the applicant’s state
of knowledge and when grounds first arose.
32. That is highly material here. There was an obvious need for
arrangements to be put in place quickly for these lifeline ferry services. The urgency was in large part created by
Brittany Ferries decision not to extend the existing contract beyond March
2025. It was or should have been
obvious that binding contractual commitments would be entered into quickly
after the preferred bidder was identified. DFDS’ evidence explains the
financial and practical implications for it.
33. Brittany Ferries were alert to the factual
basis for their allegation that the Minister had failed to explain the basis
for the Jersey government’s decision in relation to termination of the
first process when that process was terminated – i.e. around 7
November. The Minister’s
remarks upon which they relied were made on 13 November. So time for bringing such a challenge
started to run from those dates. It
was not open to Brittany to ‘keep the penny and have the bun’ by
‘reserving its position’ in relation to those allegations while
both participating in the second tender process, and declining to extend its
existing service so that the essential supplies to the island would be secured
during the conduct of that process.
34. We see some force of the argument advanced,
under reference to the case of Joseph Gleave and Son Limited v Secretary of
State for Defence [2017] EWHC 238 (TCC), to the extent that it may have
been rational for Brittany Ferries to withhold the actual lodging of its
application for judicial review until after it saw whether or not it might
become academic. (If it had won the
second tender, there would have been no relief to seek). But even if Brittany Ferries thought it
had the basis for a claim, we consider that it should have been preparing its
challenge at least immediately after lodging its second tender (on 27 November)
and have been ready to lodge within days of the written decision of 4 December,
if not on that day.
35. This mattered because the Government of Jersey
could not guarantee the ongoing provision of essential supplies without a ferry
service, and Brittany Ferries had refused to extend its contract so as to
enable a less curtailed process to take place. (It is irrelevant that at a later date it
sought to reconsider that decision – by then the second process was
necessarily underway). DFDS had bid
again in good faith, and was lining up services to ensure it could fulfil its
contract with the Minister by 25 March 2025. For the Government to decide not to
proceed with this contract would have caused serious detriment to good public
administration.
36. We accordingly conclude that the application
was not brought sufficiently promptly. To grant relief on this application would
be significantly detrimental to good administration. Such is the prejudice to good
administration (and to the interests of DFDS), that we consider the delay
itself to be prima facie sufficient to set aside the leave which has
been granted.
37. We bear in mind that the arguable merits of the
underlying judicial review are a matter to be balanced against the
discretionary bar of delay (as explained in Sharma). However, for reasons we will set out in
more detail in our written judgment, we consider the arguments, so far as
arguable to be weak. We do not
consider it arguable that the Minister was in breach of any duty to give
reasons for terminating the first tender process, and accordingly we do not
consider the second process was tainted by procedural unfairness for his
failure to do so. Assuming that the
Minister’s statement to the States of Jersey on 13 November 2024 is
admissible (which we do not need to decide), we consider that the argument in
relation to apparent bias is also very weak. And even if there were an arguable case
on the failure to give adequate reasons (which the Commissioner did not
accept), this would not be sufficiently strong to outweigh the detriment to
good administration caused by delay.
In any event, the affidavit evidence now lodged on behalf of the
Minister makes good any possible inadequacy in the initial reasons given.
38. For these reasons, we set aside the leave
previously granted to apply for judicial review. In short, having regard to the test in Sharma
there is no arguable ground for judicial review which has a realistic prospect
of success which is not subject to a discretionary bar. We have indicated that we will decide
costs at a later date, if those cannot be agreed.
Authorities
Bretagne
Angleterre Irlande SA v Minister for Sustainable Economic Development
[2024] JRC 292.
Sharma v Browne-Antoine [2006] 1 WLR
780.
Bretagne
Angleterre Irlande SA v Minister for Sustainable Economic Development
[2024] JRC 297.
Joseph Gleave and
Son Limited v Secretary of State for Defence [2017] EWHC 238 (TCC)